Brenner
Browning
Holt

March. 14 (ground breaking)

 

April 14 (site clearing)

April 26 (site fill)

May 13 footings

May 25 slab

 

6/3/10 wall framing

6/17/10 Roof trusses

July 19 mechanicals

Mar 23

stucco and drywall